roadsMedium priorityopen

SR 71/91 Interchange Completion

Riverside County

Summary

The Corona interchange project is nearly done — the new connector bridge opened in June 2025 — but unexpected boulders and buried concrete drove up costs, requiring a $2.3 million contingency increase to close out. It stayed within the overall budget.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Mar 11, 2026.

Impact analysis

💰Financial impact

$2.3 million more in contingency, but the project stays within its original $137.3 million budget.

✅Who benefits

Drivers merging between the 91 and 71 in Corona, who get improved flow and a new direct connector.