The Corona interchange project is nearly done — the new direct connector bridge opened in June 2025 — but surprise underground conditions required $2.3 million more in contingency. The project stays within its original budget.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Feb 23, 2026.
Impact analysis
An added $2.34 million in contingency, covered by existing construction funding.
Drivers using the 91/71 interchange in Corona get smoother, safer connections.