Summary
RTA is spending $6.85 million to upgrade its Hemet-area bus facility so it can take over fixed-route bus operations from a contractor. The project adds a two-story office building, maintenance bays, and safety systems.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Jun 25, 2026.
Impact analysis
$6,228,945 contract plus $622,895 contingency, covered by the board-approved capital budget.
Riders benefit from a smoother transition to in-house bus operations; local construction workers get the contract.